Gable Road Construction Update

Construction crew working on street paving next to new sidewalks

Gable Road: US30 - Columbia Blvd, Sidewalks
Project update from Columbia County Public Works Department 
September 1- September 7 Update
 

 

 

This week:

  • The north side of the road was paved between the Safeway bottle drop exit and the Avamere entrance.
  • The last (west) high school driveway was paved along with the south side of Gable road in front of the driveway.
  • The full width of the road was opened to two-way traffic between HWY 30 and the Avamere entrance.
  • Temporary striping was installed for the crosswalk between the high school and Safeway property.
  • A temporary asphalt walkway was paved in front of the construction staging yard near Safeway.
  • Crews began staging materials along the road west of Rockwood drive in preparation for continued storm work.

Next week:

  • TFT will resume work on the new storm system starting just west of Rockwood drive and working towards Columbia Blvd.
  • NOTE: Traffic delays are expected for the next few weeks between Rockwood Dr and Greenbrier Lp while the new storm system is installed.
  • There is potential for more rock hammering during the storm work.

Click any thumbnail image to view a slideshow

Construction work and equipment on road with unpaved road and new sidewalks installed